Oceanside Harbor dredging program nears end

Manson Construction met the contract amount of 245,000 cubic yards of sand as of Friday night, May 13, according to the latest Oceanside Harbor Dredge Update. They continued to dredge until Saturday 2:30pm, the official statement said. The final dredged amount will be determined at a later date. The

1 minutes read
Oceanside Harbor dredging program nears end
City of Oceanside Harbor

Manson Construction met the contract amount of 245,000 cubic yards of sand as of Friday night, May 13, according to the latest Oceanside Harbor Dredge Update.

They continued to dredge until Saturday 2:30pm, the official statement said.

The final dredged amount will be determined at a later date.

The HR Morris dredge vessel departed the Harbor on Sunday, May 15 at 10am.

No land demobilization will take place on Sunday. Today, pipeline south of the City pier and under the pier will be removed.

Tuesday, pipeline by North Coast Village and at the mouth of the San Luis Rey will be removed.

Advertisement

On Wednesday, pipeline between NCV and the City pier will also be removed. Heavy equipment will operating on the beach during the demobilization of the pipeline and for several days thereafter.

Demobilization of all equipment and vessel should be complete by Wednesday, May 25.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.