DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Final caisson arrives at Aberdeen Expansion site
Infrastructure

October 12, 2021 · about 4 years ago

Final caisson arrives at Aberdeen Expansion site

The £350 million Aberdeen South Harbour expansion project has reached another milestone with the arrival and placement of the final concrete caisson. All 22 caissons are in place at the expansion site, forming the basis of the closed quay section of the North Quay, the East Quay and South East Pier.

2 minutes read
  • LinkedIn
  • X
  • Email
Final caisson arrives at Aberdeen Expansion site
Aberdeen Harbour Board

The £350 million Aberdeen South Harbour expansion project has reached another milestone with the arrival and placement of the final concrete caisson.

All 22 caissons are in place at the expansion site, forming the basis of the closed quay section of the North Quay, the East Quay and South East Pier.

The eight-thousand-tonne blocks were made in La Coruna, Spain, and transferred to the Cromarty Firth for storage before being individually towed to the expansion site. The first caisson arrived in the project site in February 2019.

The caissons are approximately 50 metres long and between 12 – 15 metres wide, with a depth of approximately 15 metres.

Keith Young , AHEP Project Director, said: “The safe arrival and placement of the final caisson is a huge achievement for all those involved in the project, and my particular thanks go to those within the AHEP team, and at Cromarty Firth, Ocean Kinetics, Caledonian Towage and Pirie & Smith.

“The caissons form a key part of the Harbour structure, and will give customers and port users incredible heavy lift capacity – as many as 15 tonnes per square metre. This will be crucial for a variety of complex operations associated with the industries we serve.

“Work will now continue on the top layers of the fixed quays. We have seen considerable progress on site over the summer months, particularly with the South Breakwater and Crown Wall, and are on track for our phased completion in 2021 and into 2022.”

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Infrastructure

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Partner Stocznia, Vuyk sign contract for new TSHD
  2. 2Western Bay of Plenty District: $576,000 upgrade for Katikati seawall
  3. 3Protecting Sri Lanka's coastal biodiversity
  4. 4PHOTO OF THE DAY: Modi R wraps up Geraldton dredging

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free