Lhaimagu Harbor development scheme in full swing

Infrastructure

Maldives Transport and Contracting Company (MTCC) has just released the latest update on the Sh. Lhaimagu Harbor development project.

MTCC

According to MTCC, the dredging works in the new harbor basin are currently ongoing, with 78% completion so far.

The first shipment of rock boulders required for breakwater construction was successfully delivered to the project site on March 13.

MTCC photo

The Sh. Lhaimagu Harbor project includes:

  • dredging and excavation operations of 31,000cbm;
  • construction of a 350m breakwater;
  • a 276m quay wall;
  • a 500m revetment;
  • installation of 1,380sqm pavement, installation of navigation lights and streetlights.

The value of the project is MVR 56.3 million ($3.6 million).