DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Queen Bess Restoration Project Nears End
Business & Finance

February 2, 2020 · about 6 years ago

Queen Bess Restoration Project Nears End

The Queen Bess Island project, one of the fastest moving restoration projects Louisiana has seen, is nearing its completion. There is only a window of six months to complete the project during the non-nesting season in order for the birds to be able to lay eggs in the spring. “One of the nuisances o

2 minutes read
  • LinkedIn
  • X
  • Email
Queen Bess Restoration Project Nears End
Image source: LSU

The Queen Bess Island project, one of the fastest moving restoration projects Louisiana has seen, is nearing its completion.

There is only a window of six months to complete the project during the non-nesting season in order for the birds to be able to lay eggs in the spring.

“One of the nuisances of this project is they did not want any construction occurring when the birds show up to nest,” said LSU Biological Engineering alumna Amanda Phillips. “ Pelicans tend to nest where they were born. There could be large ramifications if their nesting were affected. Wildlife and Fisheries really wanted the construction to happen after nesting season, which is after Sept. 15 and before nesting season starts on March 15.”

Now in its final stages, the Queen Bess Island project will provide 30 acres of restored brown pelican and wading bird habitat, along with seven acres of nesting tern and black skimmer habitat.

In order to increase the island to 37 acres, sediment had to be dredged from the Mississippi River near Belle Chase and then barged to the site. The sand was then poured to help elevate the island.

Contractors sloped the island from the highest elevation at the southwest end and the lowest at the northeast end.

The project will make marsh habitat accessible for fish and protect it with a breakwater to reduce wave and tidal erosion. A row of breakwaters on the south side of the island will also give young birds a safe, calm area for swimming with easy access to the water. Limestone will cover about one-third of the island to provide habitat for other bird species looking for beachfront property.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Boskalis: Geopolitical tensions in the Middle East adversely impact activity levels
  2. 2Anaklia dredging project accelerates with two Jan De Nul TSHDs in the area
  3. 3VIDEO: Damen TSHD Kapuka gears up for sea trials
  4. 4Spotlight on Tuvalu Coastal Adaptation Project in Funafuti

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free