DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Preparations Underway for Manasota Key Beach Renourishment
Business & Finance

January 7, 2020 · about 6 years ago

Preparations Underway for Manasota Key Beach Renourishment

The preparation activities for the Manasota Key Beach Renourishment Project, to be conducted by Great Lakes Dredge & Dock Corporation (GLDD), are currently underway. The mobilization is set to begin in the following days and will last until the beginning of February. Once mobilization is complete, t

1 minutes read
  • LinkedIn
  • X
  • Email
Preparations Underway for Manasota Key Beach Renourishment
Image source: GLDD

The preparation activities for the Manasota Key Beach Renourishment Project, to be conducted by Great Lakes Dredge & Dock Corporation (GLDD), are currently underway.

The mobilization is set to begin in the following days and will last until the beginning of February.

Once mobilization is complete, the sand placement will begin on the Charlotte County portion of Manasota Key. The contractor will complete the Charlotte County beach fill on Manasota Key and then move North into Sarasota County.

All work on Manasota Key will be completed prior to Sea Turtle nesting season.

The initial project proposes to discharge 1,009,000 cubic yards of beach compatible sand inclusive of the design beach, advance nourishment, equilibrium template, construction tolerance and tapers to restore the critically eroding shoreline of Manasota Key between R175 (Sarasota County) to R15.4 (Charlotte County).

The County permitted five offshore borrow areas for their existing Erosion Control Project and have identified three new offshore borrow areas, for a total of eight offshore borrow areas to provide the sand for initial construction and subsequent renourishment.

The beach fill will impact 2.1 acres of persistent and 2.5 acres of ephemeral nearshore hardbottom.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Willapa Harbor dredging underway
  2. 2Dredging begins on Gugu River in Pampanga
  3. 3Boskalis Nederland: Work on Fish Migration River Afsluitdijk in full swing
  4. 4New sand arrives at West Beach and Henley Beach South

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free