DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Manila Bay Dredging Continues Despite Bad Weather
Business & Finance

March 13, 2019 · about 7 years ago

Manila Bay Dredging Continues Despite Bad Weather

The Philippines’ Department of Public Works and Highways (DPWH) is looking to take advantage of the El Niño by continuing its dredging and desilting operations in Manila Bay. According to the PNA, DPWH-Bureau of Equipment (BOE) Director Toribio Ilao announced that though the effects of such weather

2 minutes read
  • LinkedIn
  • X
  • Email

The Philippines’ Department of Public Works and Highways (DPWH) is looking to take advantage of the El Niño by continuing its dredging and desilting operations in Manila Bay.

According to the PNA, DPWH-Bureau of Equipment (BOE) Director Toribio Ilao announced that though the effects of such weather condition for some are damaging, for them it is advantageous as the waves and underwater currents are manageable to continue the cleaning activities.

“ It’s good for us because the waves and underwater current are not that strong. The excavator could go farther. The tidal effect is lower than if there’s no El Niño ,” Toribio Ilao said.

Ilao reported that as of Monday, they have collected approximately 3,000 cubic meters of silt and garbage, including 44 rubber tires. Currently, they are operating with three trucks as maximum but they are looking at adding 20 to 30 trucks in the next two weeks.

As for the machines, Ilao said that they have four amphibious excavators and one land-based crawler excavator that are operating from Monday to Saturday.

DPWH Secretary Mark Villar visited the area located near the US Embassy in Manila to personally see the progress of the dredging and desilting operations.

Last week, the DPWH, together with the Department of Environment and Natural Resources, the local government of Manila and other stakeholders, launched the Desilting Operations dubbed “DPWH Sagip Manila Bay” to clean the 1.5-kilometer stretch of the Bay from the Manila Yacht Club breakwater to the US Embassy.

The desilting activities will be divided into five sectors, each ranging from 200 to 300-meter long, until the entire 1.5-kilometer is finished. Each sector will be desilted approximately within 90 to 120 days.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EIB provides EUR100M for Klaipėda Port development
  2. 2South Hayling beach management works on the way
  3. 3DEME opens new Soil Wash installation at Schiphol Airport
  4. 4Lorain Harbor dredging kicks off

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free