DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›VBA Starts Phase Two of the Church Scar Coast Protection Scheme
Business & Finance

October 30, 2018 · about 8 years ago

VBA Starts Phase Two of the Church Scar Coast Protection Scheme

VBA – a joint venture comprising VolkerStevin, Boskalis Westminster and SNC-Lavalin’s Atkins business – is starting the next phase of works at Fairhaven Lake. According to VBA, the second phase of works at Fairhaven Lake will involve upgrading Stanner Bank car park, replacing the retaining wall and

1 minutes read
  • LinkedIn
  • X
  • Email

VBA – a joint venture comprising VolkerStevin, Boskalis Westminster and SNC-Lavalin’s Atkins business – is starting the next phase of works at Fairhaven Lake.

According to VBA, the second phase of works at Fairhaven Lake will involve upgrading Stanner Bank car park, replacing the retaining wall and refurbishing the existing outfall drainage from Fairhaven Lake to the sea.

This £17.5m coastal protection project is a partnership between Fylde Council, VBA and the Environment Agency.

Overall, the Fylde Coastal Protection scheme includes replacement of the current concrete defenses along the two mile stretch between Fairhaven and Church Scar at Lytham St Annes.

Work on the project began in February 2018 with the installation of sheet piles which were carried out by piling specialists VolkerGround Engineering, to secure the foundations for the new concrete retaining wall.

The earthworks then followed establishing the temporary route at Church Scar to enable VBA to begin the removal and replacement of the existing retaining wall.

The whole project is due for completion in 2020.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Sinocalan River dredging project on the way
  2. 2NSW Government: Applications open for Boating Infrastructure Maintenance Program
  3. 3EXCLUSIVE: Charlotte Amalie dredging starts next month
  4. 4Dredger picks up 150 kg German bomb off Belgian coast

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free