DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Town of Sandwich Dredging Permit on the Table
Business & Finance

August 21, 2018 · about 8 years ago

Town of Sandwich Dredging Permit on the Table

The Town of Sandwich is seeking a permit from the U.S. Army Corps of Engineers, New England District to conduct work in waters of the U.S. in conjunction with dredging off of Scusset Beach and placing the material on Town Neck Beach in Sandwich, Mass. The dredging work is proposed in Cape Cod Bay of

1 minutes read
  • LinkedIn
  • X
  • Email

The Town of Sandwich is seeking a permit from the U.S. Army Corps of Engineers, New England District to conduct work in waters of the U.S. in conjunction with dredging off of Scusset Beach and placing the material on Town Neck Beach in Sandwich, Mass.

The dredging work is proposed in Cape Cod Bay off Phillips Road, Scusset Beach and disposal is proposed in Cape Cod Bay at Town Neck Beach in Sandwich.

The proposed work involves the excavation of up to 224,500 cubic yards of sand and gravel materials from a 23-acre subtidal borrow site off Scusset Beach in Sandwich.

According to the Corps, the borrow site is a 17,000-foot long by 600-foot wide rectangle with depths ranging from -7 feet mean low water (MLW) to -17 feet MLW. The excavation depth will be from 1 foot to 11 feet.

This material will be hydraulically dredged with a pump-out cutter-head hopper dredge and transported to Town Neck Beach, where it will be pumped out onto the beach, dewatered, and used for dune and beach reconstruction.

The excavation is expected to be completed within two months and will be done between the months of November and March.

Deadline for sending public comments on the proposed work is September 21, 2018.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free