DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Gulf Cobla Busy in Maldives
Business & Finance

August 1, 2018 · about 8 years ago

Gulf Cobla Busy in Maldives

Pearl Atoll Pvt. Ltd. Maldives company has engaged Gulf Cobla Tennssor Maldives (GCTM) to complete the reclamation of Feydhoo Finolhu for their resort development in Kaafu Atoll. The project was stalled and delayed for a long time since Breeman Maldives, who was initially awarded the project during

1 minutes read
  • LinkedIn
  • X
  • Email

Pearl Atoll Pvt. Ltd. Maldives company has engaged Gulf Cobla Tennssor Maldives (GCTM) to complete the reclamation of Feydhoo Finolhu for their resort development in Kaafu Atoll.

The project was stalled and delayed for a long time since Breeman Maldives, who was initially awarded the project during 2017, failed to complete the dredging and reclamation of some 250,000 cubic meters of material.

“ After clearing the site, the cutter suction dredger Garhoud Bay of Gulf Cobla started within days to complete the reclamation of 6 Ha of land. GCTM satisfactorily completed the reclamation within the timeframe set by the client and the development of the resort is now back on track again ,” GCTM said.

Gulf Cobla‘s Garhoud Bay was also deployed at the Velana Airport expansion project where 6 million cubic meters was reclaimed for the major expansion of the international Airport on Hulhule island during 2017. In the summer of 2018, the Garhoud Bay has returned and is again engaged with the airport development, dredging and reclaiming for the South Harbor on Hulhule island.

GCTM is currently doing further variation orders instructed by Maldives Airport Company Limited for the shore protection scope of the airport contract, constructing rock revetments on reclaimed land and installing remaining sheetpiles along the new runway.

In addition, they were also awarded the installation of floating jetties near the new international terminal building.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free