Hull Coastal Protection Scheme About to Begin

Business & Finance

A seawall at Nantasket Beach will have its center section fortified as part of the Nantasket Beach Hurricane and Storm Damage Reduction project in Hull, Massachusetts.

George R. Cairns & Sons, Inc., of Windham, New Hampshire will do the work under a $2,696,200 contract.

The project consists of installing an approximately 2,200-linear-foot stone toe revetment along the seawall at Nantasket Beach Reservation on Hull Shore Drive,” said Project Manager Michael Riccio.

The New England District and the DCR executed a Project Partnership Agreement in April 2016 for the final design and construction of the project.

According to Riccio, work on the revetment will include shoreline excavation of about 27,000 cubic yards of beach material, placement of approximately 4,000 square yards of geotextile fabric, placement of about 1,600 cubic yards of ground and crushed stone, placement of about 4,000 cubic yards of 350-pound stone, placement of approximately 10,000 cubic yards of 2-3 ton armor stone, placement of approximate 30, 6-foot by 3-foot by 2-foot granite slabs, and backfilling of the revetment with excavated beach material.

The Massachusetts Department of Conservation and Recreation manages the beach and is the project sponsor.

Construction is set to begin by the end of this month and is expected to be completed by the end of May 2018.

[mappress mapid=”24921″]