Port of Genoa: Embracing Responsibility in Infrastructure Upgrade

Business & Finance
Mr. Marco Vaccari

The Port of Genoa is one of the major Italian seaports in the Mediterranean sea. With a trade volume of 50 million tonnes and 2-million TEUs, it is the busiest port of Italy by cargo tonnage.

Genoa Port covers an area of about 700 hectares of land stretching along the coastline, with 47 km of maritime ways and 30 km of operative quays.

At the 7th Dredging & Land Reclamation Asia Summit 2017 (organized by Equip Global, Singapore) Mr. Marco Vaccari, the Portfolio & Project Manager in the Technical Department of the Genoa Port Authority, introduced a case study about challenging experiences in the Port of Genoa construction and development with global counterparts operating ports, harbors and marine construction project developers.

The case study was about “Dredging & Land Reclamation in development of two new container terminals in Genoa port challenges and solutions”.

Q: Genoa Port has been subject of uninterrupted development since 2001 with 2 grand master plans. What are the goals and directions?

Mr. Marco Vaccari: The first Port Master Plan was approved in 2001 based on the new Italian Law 84/94, where Port Authorities would assume new functions and primary roles in planning, infrastructure development in close collaboration and dialogue with the municipality and regional government. In this context, the Genoa Master Plan has foreseen the construction of 2 new container terminals in the commercial area: Calata Bettolo and Ronco Canepa.

Calata Bettolo is located in the Eastern part of the commercial area, characterized by a total area of about 300.000m², 750-meter-long berth, and water depth at 17m. The project involved dredging of about 2.5 million m³ in sand & rock and land reclamation of approximately 180,000m². Works had started in 2007 and today are completed.

Land Reclamation at Ronco Canepa

Ronco Canepa, located in the western part of the commercial area, characterized by total area of about 170.000m², 640-meter-long berth and water depth at 15m. The project involved river mouth maintenance dredging of about 1 million m³ of mainly sand and reclaiming a land area of about 65,000m². Works had started in 2009 and are still on going.

The most recent Port Master Plan, developed in 2015, is a bold response to the need to identify a new model for port development, in collaboration with local government and the other public and private stakeholders, aimed at improving relations between the port and the city, which in Genoa live side by side.

Q: Being the largest seaport in Italy and one of Europe’s busiest, with over 51 million tonnes of trade volume each year, the 2001 Genoa Port Masterplan must have invoked many challenges with construction & engineering methodology, potential damage to environment, disruption to transhipment?  

Mr. Marco Vaccari: As a matter of fact, the two different projects (Calata Bettolo and Ronco Canepa) faced the same challenges and constraints with regards to dredging & land reclamation issues. These challenges have been managed throughout all project phases, from planning & design phase until delivering.

Challenges were first connected to the port’s positioning, due to its intimate proximity with the city. Being adjacent to the airport also imposes severe constraints even during construction phases. The Genoa port also poses a complex reality, due to the different commercial interests & multiple operators and stakeholders.

Firstly, it was necessary to guarantee port & terminal operations along the entrance and the main channel during the construction phases. Therefore, dredging activity was regulated in close connection with harbor-masters and according the availability of areas to dredge. This constraint had to be managed in advance, both across the detailed design and within the contract, so as to avoid claims from the general contractor.

The variety of areas extension and materials to dredge also meant employment of different types of dredging equipment that had to be deeply analysed in advance. From for the environmental point of view the Italian law on dredging and land reclamation (D. Lgs. N° 152/06) was very strict, making related works time-consuming. It was necessary to implement chemical analyses and characterization in advance for the entire port seabed in order to avoid dredging disruption and claims from the general contractor.

Projects: Calata Bettolo and Ronco Canepa

In addition, due to proximity to the urban waterfront, during dredging operations it was necessary to maintain constant control the turbidity levels and find the best trade-off with marine equipment.

Finally, dredging had to be performed in compliance with structural stability of existing structures, so the detailed design imposed the depth and distance from existing quays and berths.

Dredging was for maintenance purpose in both cases: in the Calata Bettolo project the huge dredging activity all along the channel and quays allowed the port to accept bigger vessels, whereas in Ronco Canepa the huge dredging activity along a river estuary was beneficial to river safety conditions, reducing flooding risk upstream.

Last but not least, it was necessary to adhere to funding and time schedule.

The realisation of these terminals using dredged materials instead of quarry materials has been a money-saving but time-consuming solution. Moreover, this solution imposed some technical & environmental constraints that had been managed both in the construction phase and in the delivering phase.

Q: What have been the outcomes of the projects and lessons learned?

At the time being one of the projects is in the delivering phase, while the other is close to completion. Main outcomes are as follows:

Benefits:

  • Financial benefit: Large maintenance works at port authority usually benefits from co-funding with local administration;
  • Economic benefit: Employment of dredging materials instead of quarry materials for the realization of terminals turned out to be a much more cost-effective solution. 3.5 million m³ of dredging material should have been discharged in an authorized landfill and this procedure would have been very expensive;
  • Social benefit: Works have been performed at sea with state-of-the-art marine equipment and dredgers, so that environmental impact of dust and traffic did not affect the waterfront and the city.

Disadvantages:

  • The combination of risk mitigation solutions connected with dredging operations and time-consuming activities on consolidation of dredged materials (compared to the employment of quarry materials otherwise) increased the time required for projects delivery;
  • Due to large volume of dredging material and strict environmental requirements of Italian Law, technical constraints had to be faced and managed during the delivering phase of the terminal. As an example, once project has been delivered, the port operator may plan to build on his own a structure with foundations on land reclamation just realized. Then the material excavated from the body of the reclamation must be handled and disposed accordingly to the strict environmental regulations given by the Italian Law.

The bottom line is that the employment of dredged materials for the realization of terminals could lead to significant cost savings but it leads to much longer delivering time. Ship construction and naval giants evolve much faster than port infrastructure, so terminal requirements on vessel dimensions in ten years had changed dramatically.

To overcome this challenge, it is beneficial to overestimate vessel dimension (draft, width and LOA) at the design phase.

(co-contributed by Tony Tran)