DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Phase 1 of the Muddy River Project Completed
Business & Finance

July 4, 2016 · about 10 years ago

Phase 1 of the Muddy River Project Completed

Construction activities are coming to a close on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Massachusetts. On Monday, June 27th, the final temporary river diversion steel sheeting was removed from upstream of the new Riverway Culve

1 minutes read
  • LinkedIn
  • X
  • Email

Construction activities are coming to a close on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Massachusetts.

On Monday, June 27th, the final temporary river diversion steel sheeting was removed from upstream of the new Riverway Culvert and the Muddy River was flowing freely and completely through the entire Phase 1 project, from the new Riverway Culvert at the upstream end, through the new Brookline Avenue Culvert and finally through the existing Avenue Louis Pasteur Culvert at the downstream end.

This marks a huge milestone for the project as the river has been running in twin 72” culverts since the 40’s between the former Riverway Intake Structure and at Brookline Avenue.

Over the past several months, the contractor for the Muddy River Phase 1 construction project has been busily excavating sediment from the river bottom at upstream Riverway, demolishing the existing Riverway Intake Structure; excavating the former Sears Parking Lot to construct the new flood risk management channel; and removing the existing twin 72” culverts.

These efforts have culminated in the river flowing once more in its natural riverine state as part of the Emerald Necklace, as well as providing a welcomed park environment in the city.

[mappress mapid=”22638″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free