DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›UPDATE: Lodgemore Dredging Project on Track
Business & Finance

September 18, 2014 · about 12 years ago

UPDATE: Lodgemore Dredging Project on Track

Land & Water Services are making excellent progress dredging the canal between Wallbridge Lower Lock and Lodgemore Bridge. The first work boats in eighty years recently arrived on this stretch of water. Two brand new mud hoppers and a mini push tug are also in the place. The mud hoppers were manufac

2 minutes read
  • LinkedIn
  • X
  • Email

Land & Water Services are making excellent progress dredging the canal between Wallbridge Lower Lock and Lodgemore Bridge.

The first work boats in eighty years recently arrived on this stretch of water. Two brand new mud hoppers and a mini push tug are also in the place.

The mud hoppers were manufactured in Birmingham. They will be used to transfer dredged material along the length of newly navigable water.

Cost saving ingenuity

An ingenious cost saving and environmentally sound method of retaining the material on site has been adopted. The northern bank margin which borders onto the rear aspect of Homebase has been reshaped to provide the repository for hundreds of cubic metres of silt.

Environmental benefits explained

Senior Site Manager Chris Spencer said: “Off-site disposal of dredged material to landfill is expensive. So, to save costs for Stroud District Council, we have re-shaped the north bank by creating a flat top, a sort of shelf if you like… We then created a raised bank at the front of the shelf and along its full length. The long reach of the WK80 tracked amphibious excavator allows us to move the material up onto the new flat area behind the banked edge. This process allows the silt to drain and go firm.”

Next step

Wallbridge Lower Lock is due for refurbishment in Spring 2015. However, some time is to be saved by the Land & Water team whilst they are on site. The company has been tasked with removing the dangerously tilted wall overhanging the lock and to clear material from the lock itself. This will also provide a clearer picture of the structural integrity of the lock.

Funding

Work along this stretch is being funded with the assistance of a £100,000 grant from the Veolia Environmental Trust.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Bahrain plans major land reclamation at Khalifa Port
  2. 2Precision dredging at Newton Ferrers by TMS
  3. 3Two months to go: get your ticket for OEEC 2026
  4. 4PHOTO OF THE DAY: Dredge Potter returns for 2026 dredging season

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free