DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Mississippi River Emergency Dredging Wrapped Up (USA)
Business & Finance

August 10, 2014 · about 12 years ago

Mississippi River Emergency Dredging Wrapped Up (USA)

The U.S. Army Corps of Engineers, St. Paul District, completed emergency dredging operations in the Mississippi River on August 7. The Corps dredged temporary 200-feet wide pilot channels in both Pool 4, between Wabasha, Minn., and Alma, Wis., and in Pool 6, near Winona, Minn. The pilot channels all

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, St. Paul District, completed emergency dredging operations in the Mississippi River on August 7.

The Corps dredged temporary 200-feet wide pilot channels in both Pool 4, between Wabasha, Minn., and Alma, Wis., and in Pool 6, near Winona, Minn. The pilot channels allowed the U.S. Coast Guard to officially reopen the 9-foot navigation channel to commercial traffic. The normal authorized channel width is 300 feet. It was originally closed July 19, near Wabasha, and July 23, near Winona.

The Corps completed dredging in Pool 4 yesterday, and the Coast Guard reopened the channel without any restrictions. The channel in Pool 6 was reopened August 3, but required restrictions on the barge configurations. There are no longer any restrictions within either pool.

In all, the Corps had two government dredging operations, the Dredge Goetz and a mechanical dredging crew, along with two contract mechanical dredging operations. Dredging began July 16 when the water elevations were low enough to begin. Collectively, the dredges removed more than 290,000 cubic yards of dredged material from the river. This is nearly 30 percent of the average material removed during an entire year, and it’s enough material to fill a line of 10-cubic-yard dump trucks from Minneapolis to La Crosse, Wis.

In addition to the dredges, the Corps used two channel survey boats to monitor the river channel depth. The surveyors will continue looking for shallow areas in the coming weeks. Together with the dredges, the Corps expects to continue maintenance dredging into the fall.

The Corps coordinated daily with navigation industry officials and the U.S. Coast Guard to ensure everyone understood what was being done to reopen the channel.

[mappress]

Press Release, August 11, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free