WSHD Plans Voorne Putten Dredging Works

Project & Tenders

WSHD Plans Voorne Putten Dredging Works

Waterschap Hollandse Delta (WSHD) intends to carry out the Voorne Putten dredging works to maintain and ensure adequate waterway depths for this year and next, with the contractor being eligible for the 7-year maintenance cycle.

WSHD has chosen the work to be carried out with an integrated contract (based on the UAV-GC 2005) for both the design and execution of the works.

The work will start on August 05, 2014, and it is planned to last until March 15, 2016.

The contractors interested in performing the project should submit their tenders no later than June 30, 2014.

The tenders are required to be in Dutch.

Dredging Today Staff, May 30, 2014