VIDEO: River Parrett Dredging Progresses Well (UK)

Business & Finance

River Parrett Dredging Progresses Well

The Environment Agency is currently dredging at both banks of the River Parrett downstream of Moorland House Farm.

They have so far removed over 7,600m³ of silt along a 445 metre length. There are currently 3 excavating machines working 5 days a week.

Over the next couple of weeks the following activities will take place:

– Dredging will continue downstream of Moorland House Farm on both banks of the River Parrett;

– EA will be moving into the main compound at Gillards in Burrowbridge.

[mappress]

Dredging Today Staff, May 20, 2014