DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Peters Concrete Bags Renard Island Dredging Deal
Business & Finance

September 30, 2013 · about 13 years ago

USA: Peters Concrete Bags Renard Island Dredging Deal

The U.S. Army Corps of Engineers, Detroit District, awards a contract for covering Renard Island, an inactive dredged material placement site located in Green Bay, Wis. The $1,909,300 contract was awarded to Peters Concrete Co., Green Bay, Wis. The firm will remove about 250,000 yards of clean sedim

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Detroit District, awards a contract for covering Renard Island, an inactive dredged material placement site located in Green Bay, Wis.

The $1,909,300 contract was awarded to Peters Concrete Co., Green Bay, Wis. The firm will remove about 250,000 yards of clean sediment from the Bayport Confined Disposal Facility, CDF, in the city of Green Bay and use it to put down a 3-foot cover on the Renard Island placement site.

“Beneficial reuse of dredged material is always a win-win, ” said Lt. Col. Robert Ells, district engineer . “Reusing dredged material from an active facility to cover the island allows us to extend the life of the Bayport facility while closing out Renard Island, which has served the community for many years. We are pleased to get this project underway.”

Renard Island served the Green Bay region for nearly two decades as the placement site for sediment from maintenance dredging activities. Located near the mouth of the Fox River about two miles southeast of Bayport CDF, the 55-acre island was constructed in 1979 and was used for dredged material disposal through 1996.

The contract calls for completion of work by spring 2015. Most of the work will be done in late fall to early spring months when the Bayport CDF soil is hard enough to support excavation equipment.

[mappress]

Press Release, October 1, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free