CHC Publishes Timeline for New Cowes Breakwater (UK)

Business & Finance

CHC Publishes Timeline for New Cowes Breakwater

Cowes Harbour Commission (CHC) has published a preliminary timeline for the construction of the new Cowes breakwater.

The breakwater will be delivered under a design and build, fixed priced contract.

Construction is likely to take around eight months, depending on the methodology employed by the contractor, with completion during 2014.

More info

[mappress]

Press Release, September 26, 2013