DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›GPC: Bund Wall in Gladstone Harbour is Not Leaking (Australia)
Business & Finance

June 24, 2013 · about 13 years ago

GPC: Bund Wall in Gladstone Harbour is Not Leaking (Australia)

The Gladstone Ports Corporation makes an announcement to reassure the Gladstone and wider community that the reclamation area or bund wall in the Gladstone harbour is not leaking. The ABC television 7pm News on Friday 21 June reported the bund wall was leaking with images of water discharging out of

2 minutes read
  • LinkedIn
  • X
  • Email

The Gladstone Ports Corporation makes an announcement to reassure the Gladstone and wider community that the reclamation area or bund wall in the Gladstone harbour is not leaking.

The ABC television 7pm News on Friday 21 June reported the bund wall was leaking with images of water discharging out of the bund wall – this is incorrect. On Friday 14 June, a polishing pond weir box situated on the inside of the bund wall was not sealing properly and was fixed over the weekend of the 15 and 16 June.

The ABC report and subsequent images on Friday 21 June were of a normal regulated discharge that happens every day in the Western Basin.

To clarify, dredge soil is transported by the dredgers as a slurry of water and spoil, the spoil being retained in the reclamation and the water returned to the environment through the licensed discharge point.

As the dredge soil is deposited, the heavier and larger materials are immediately deposited, with the finer materials remaining suspended in the water. The reclamation is divided into three distinct areas, the main reclamation, the ‘siltation pond’ and the ‘outlet channel.’ The system is designed so that as the water travels through each area a percentage of the finer materials settle’s out of suspension.

Discharge water quality is achieved through decanting the clean upper layer of water from each area so that by the time the water reaches the discharge point, the licensed discharge criteria is met. This process is what the ABC filmed on Friday afternoon, not a leaking bund, but a regulated discharge.

The claim by commercial fisherman Trevor Falzon that the water discharged is toxic is incorrect. All controlled water releases from the reclamation area are monitored for water quality. The extensive independent environmental water quality monitoring program for the Western Basin Dredging and Disposal Project (WBDDP) shows no visible or scientific signs of any negative impact from changes in water quality to date.

The Water Quality Monitoring Program is overseen by the Dredge Technical Reference Panel appointed by the Federal Minister for Sustainability, Environment, Population and Water.

[mappress]

Source: westernbasinportdevelopment, June 25, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free