DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Wiggins Pass Beach and Channel Ready for Visitors
Business & Finance

May 21, 2013 · about 13 years ago

USA: Wiggins Pass Beach and Channel Ready for Visitors

All dredging requiring sand placement or interface with Wiggins Pass Beach was completed by May 1 as required by permit to avoid turtle nesting season. A total of 94,000 cubic yards of materials have been placed or removed during the $1,754,000 pass maintenance project conducted by contractor Orion

1 minutes read
  • LinkedIn
  • X
  • Email

All dredging requiring sand placement or interface with Wiggins Pass Beach was completed by May 1 as required by permit to avoid turtle nesting season.

A total of 94,000 cubic yards of materials have been placed or removed during the $1,754,000 pass maintenance project conducted by contractor Orion Marine Construction. Dredging activity included straightening the Wiggins Pass S-shaped channel.

During dredging, an unexpected 2,000 to 4,000 cubic yards of hard-packed material, including rock fragments and consolidated shells, was encountered. Removal of this material is continuing for approximately two more weeks with excavation using a backhoe and barge. The hard material will be disposed of in a former borrow area about two miles off shore.

Despite being peak tourist season, the schedule mandated by permit was for beach work to be conducted during the two months prior to turtle nesting season.

In the past 20 years, Wiggins Pass has been dredged 13 times and needs repeat work more often since it has been refilling with sand with increased frequency. Historically, the pass has been dredged every two years but recent trends have the channel filling in every 18 months to un-navigable conditions. In addition to unsafe boating conditions, Barefoot Beach and the mangrove channel to the north have experienced significant erosion.

[mappress]

Press Release, May 22, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Boskalis and Van Oord begin IJsselmeerdijk project
  2. 2USACE completes West Harbor dredging project
  3. 3EXCLUSIVE: GRSE, Damen sign MoU on construction of advanced dredgers
  4. 4Lyttelton Port gears up for its largest expansion project

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free