DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Australia: Augusta Harbour Development Moves Ahead
Business & Finance

April 22, 2013 · about 13 years ago

Australia: Augusta Harbour Development Moves Ahead

The new Augusta Boat Harbour, funded by the State Government’s Royalties for Regions program, is taking shape with the footprint of the two breakwaters now complete. Department of Transport (DoT) Project Manager Stephen Smith said both the 150 metre northern breakwater and the 600 metre southern bre

2 minutes read
  • LinkedIn
  • X
  • Email

The new Augusta Boat Harbour, funded by the State Government’s Royalties for Regions program, is taking shape with the footprint of the two breakwaters now complete.

Department of Transport (DoT) Project Manager Stephen Smith said both the 150 metre northern breakwater and the 600 metre southern breakwater had been constructed to the minimum breakwater level.

“Construction activities will now progressively raise the height of the larger southern breakwater to provide adequate protection from prevailing south easterly winds and wave overtopping during storms, ” Mr Smith said.

“At the end of the southern breakwater, the structure’s most exposed location, rocks weighing up to 11 tonne each will be positioned in two layers with the aid of a 100 tonne long reach excavator.”

To date the project has seen quarrying on site of approximately two thirds (330,000 tonne) of the total 500,000 tonne of granite rock required to create the breakwaters and reclamation area.

Mr Smith said the complex environmental monitoring associated with the project was continuing with pleasing results.

“An underwater dive inspection of the outer face of the southern breakwater by local Marine Biologist Brad Adams observed the early establishment of abalone and fish populations ,” Mr Smith said.

“The completion of the breakwaters to the lower level will also see a reduction in the amount of small pieces of plastic tube used in the rock blasting process washing up on local beaches. Debris monitoring and collection will continue until August to ensure all the material is found and removed.”

[mappress]

Press Release, April 23, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free