DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›India: Mumbai Port, JN Port Spar over Dredging Costs
News

July 8, 2012 · about 14 years ago

India: Mumbai Port, JN Port Spar over Dredging Costs

According to livemint.com, the Union government-controlled Mumbai port and Jawaharlal Nehru (JN) port are sparring over sharing costs for a channel-deepening project for a common navigational channel, potentially delaying the award of contract to Dutch dredging firm Royal Boskalis Westminster NV. Ro

2 minutes read
  • LinkedIn
  • X
  • Email

According to livemint.com, the Union government-controlled Mumbai port and Jawaharlal Nehru (JN) port are sparring over sharing costs for a channel-deepening project for a common navigational channel, potentially delaying the award of contract to Dutch dredging firm Royal Boskalis Westminster NV.

Royal Boskalis had emerged as the lowest bidder for the work on 18 June by quoting Rs.1,219.8 crore which is lower than the budget of Rs.1,571.6 crore approved by the cabinet committee on infrastructure.

Livemint.com reports that though JN port had initiated the project, a major portion of the work on deepening and widening of Mumbai harbour and JN port channel falls within the channel belonging to Mumbai port.

“ The cost sharing agreed then needs to be reviewed because of cost escalation and also because Mumbai port will stand to benefit from the channel-deepening project,” a spokesman for JN port said.

“ JN port has asked us to share 50% of the project cost, which we have rejected outright, ” said a spokesman for Mumbai port. “ It’s their (JN port) project. We have agreed to share one-eighth of the cost, which is a bonus for them. Now they are becoming greedy, ” he said, adding that the port was not in favour of raising its earlier-agreed contribution for the project designed to give larger ships access to JN port.

The dredging work covers an area of 33km, out of which 26km is in Mumbai harbour and the balance in JN port channel.

The project has been delayed by at least four years and is now slated to be completed by 2014 instead of the earlier estimate of 2010, if an earlier auction had gone through.

[mappress]

Dredging Today Staff, July 9, 2012

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42