DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›USA: New Geothermal Bags May Speed Up Wares Creek Project, Says Official
News

March 29, 2012 · about 14 years ago

USA: New Geothermal Bags May Speed Up Wares Creek Project, Says Official

U.S. Army Corps of Engineers spokesperson stated that new geothermal bags were placed at Wares Creek recently. These new bags will be used to speed up the flood control project in this area, reports bradenton.com. After the dredging operations the extracted materials needed to dry out in order to be

1 minutes read
  • LinkedIn
  • X
  • Email

U.S. Army Corps of Engineers spokesperson stated that new geothermal bags were placed at Wares Creek recently. These new bags will be used to speed up the flood control project in this area, reports bradenton.com.

After the dredging operations the extracted materials needed to dry out in order to be taken away to a landfill. This process took some time in the previous geothermal bags, so the dredging had been temporarily paused. Operations resumed on Wednesday.

Amanda Ellison, a Corps spokeswoman in the Jacksonville district , said: “ These new bags brought in are bigger and they’ll be able to put more material in them. And the material should be able to dry out even faster. ”

Cedar Hammock-Wares Creek, a $51.8 million project, has an aim to reduce flooding in this area.

Dredging works were expected to be finished by April but the finding of unexpected additional sand-like sediment and equipment adjustment pushed back dredging completion to May or June.

Dan Hough, a resident on Virginia Drive near the project site, states that if the dredger was bigger and more powerful then perhaps the process would finish faster.

Follow-up works are scheduled for the Creek; the Ninth Avenue Bridge will be taken down and replaced with a new one. Channel widening will also be needed.

[mappress]

Dredging Today Staff, March 30, 2012; Image: Manatee County Government

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free