DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›UK: Port of Liverpool Development Plan Moves Forward
News

March 16, 2012 · about 14 years ago

UK: Port of Liverpool Development Plan Moves Forward

The Mersey Docks and Harbour Company Limited plans to announce a tender for dredging works at the port area. Officials’ plan is to appoint a contractor to undertake a package of dredging, quay wall construction and infilling works at “Liverpool 2” (Liverpool’s new deep water container terminal), Por

2 minutes read
  • LinkedIn
  • X
  • Email

The Mersey Docks and Harbour Company Limited plans to announce a tender for dredging works at the port area.

Officials’ plan is to appoint a contractor to undertake a package of dredging, quay wall construction and infilling works at “Liverpool 2” (Liverpool’s new deep water container terminal), Port of Liverpool, which will be located adjacent to the Royal Seaforth Dock at the Port of Liverpool.

The economic operator will be required to dredge, construct and infill (including compaction of infill material) a quay wall of the following approximate dimensions – 850m length x 30m height.

The quay wall will enclose an area of reclaimed land constituting approximately 2,500,000 m3 of predominantly dredged material. The area of reclaimed land will be surfaced (which may, at the discretion of the contracting entity, be procured under a separate package of works) to form a new deep water container terminal of approximately 22 hectares.

It is likely that the economic operator will take design responsibility for some or all of the Works. The economic operator will be required to dredge a berthing pocket in front of the new quay wall. It is anticipated that the economic operator will be required to remove approximately 1,000,000 m3 of dredged material from the quayside berthing pocket.

The source of the infill material is still to be determined, although it is anticipated that suitable dredged material may be obtained from any or all of the following sources – berth pocket dredge, approach channel dredge and maintenance dredge material obtained from the River Mersey or from commercially available sources.

These following works will also form part of this works package: capping beams, rear crane rail piles and further construction work relating to the provision of drainage and outfall extension.

The value of this project will be between £65,000,000 and £120,000,000.

[mappress] Dredging Today Staff, March 16, 2012; Image: Peel Ports

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Dredger picks up 150 kg German bomb off Belgian coast
  2. 2GLDD wins South Atlantic Regional Harbor Dredging Contract
  3. 3Meaford Harbor in-water dredging completes
  4. 4Barge with dredge material runs aground in North Vancouver

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free